Juice Tank Steelwork

Over 200 tonnes of steelwork was fabricated to create a supporting structure for two new juice tanks for British Sugar at their Bury St Edmunds site in Norfolk.

This included steelwork for structure on 3no. Levels, complete with platforms, stairs and handrailing for access to the juice tanks for maintanace personnel.

The job was divided up into 5 phases with production starting in Janaury 2014 and site installation completed in June 2014.